333 Sand & Gravel
|
Surface
|
Abandoned
|
Construction Sand and Gravel
|
|
Parties
Name
|
Austin Construction LLC
|
Role
|
Operator
|
Start Date
|
1996-03-25
|
|
Name
|
Town Of Campbell
|
Role
|
Operator
|
Start Date
|
1950-01-01
|
End Date
|
1996-03-24
|
|
Name
|
Michael Austin
|
Role
|
Current Controller
|
Start Date
|
1996-03-25
|
|
Name
|
Austin Construction LLC
|
Role
|
Current Operator
|
|
Inspections
Start Date |
2005-11-22
|
End Date |
2005-11-22
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
6
|
|
Start Date |
2004-10-26
|
End Date |
2004-10-27
|
Activity |
REGULAR INSPECTION
|
Number Inspectors |
1
|
Total Hours |
11
|
|
Start Date |
2003-12-12
|
End Date |
2003-12-12
|
Activity |
COMPLIANCE FOLLOW-UP INSPECTION
|
Number Inspectors |
1
|
Total Hours |
2
|
|
Start Date |
2003-12-05
|
End Date |
2003-12-05
|
Activity |
REGULAR INSPECTION
|
Number Inspectors |
1
|
Total Hours |
7
|
|
Start Date |
2003-09-05
|
End Date |
2003-09-05
|
Activity |
REGULAR INSPECTION
|
Number Inspectors |
1
|
Total Hours |
9
|
|
Start Date |
2002-06-05
|
End Date |
2002-06-05
|
Activity |
COMPLIANCE FOLLOW-UP INSPECTION
|
Number Inspectors |
1
|
Total Hours |
3
|
|
Start Date |
2002-04-04
|
End Date |
2002-04-04
|
Activity |
REGULAR INSPECTION
|
Number Inspectors |
1
|
Total Hours |
10
|
|
Start Date |
2001-07-03
|
End Date |
2001-07-05
|
Activity |
REGULAR INSPECTION
|
Number Inspectors |
1
|
Total Hours |
15
|
|
Start Date |
2001-07-02
|
End Date |
2001-07-05
|
Activity |
VERBAL HAZARD COMPLAINT
|
Number Inspectors |
1
|
Total Hours |
13
|
|
Start Date |
2000-10-13
|
End Date |
2000-10-13
|
Activity |
COMPLIANCE FOLLOW-UP INSPECTION
|
Number Inspectors |
1
|
Total Hours |
3
|
|
Start Date |
2000-09-14
|
End Date |
2000-09-14
|
Activity |
COMPLIANCE FOLLOW-UP INSPECTION
|
Number Inspectors |
1
|
Total Hours |
2
|
|
Start Date |
2000-08-09
|
End Date |
2000-08-10
|
Activity |
REGULAR INSPECTION
|
Number Inspectors |
1
|
Total Hours |
28
|
|
Productions
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2006
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2005
|
Annual Hours
|
1992
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
996
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2005
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2004
|
Annual Hours
|
3107
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
3
|
Avg. Employee Hours
|
1036
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2004
|
Annual Hours
|
3
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
3
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2003
|
Annual Hours
|
1800
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
900
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2003
|
Annual Hours
|
2
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
2
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2002
|
Annual Hours
|
1889
|
Avg. Annual Empl.
|
3
|
Avg. Employee Hours
|
630
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2001
|
Annual Hours
|
4940
|
Avg. Annual Empl.
|
3
|
Avg. Employee Hours
|
1647
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2001
|
Annual Hours
|
1078
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
1078
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2000
|
Annual Hours
|
3291
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
1646
|
|
|
NAAR'S PIT
|
Surface
|
Abandoned
|
Construction Sand and Gravel
|
|
Directions to Mine |
unknown
|
Parties
Name
|
Austin Construction Llc
|
Role
|
Operator
|
Start Date
|
1999-07-01
|
|
Name
|
Michael Austin
|
Role
|
Current Controller
|
Start Date
|
1999-07-01
|
|
Name
|
Austin Construction Llc
|
Role
|
Current Operator
|
|
Inspections
Start Date |
2000-08-09
|
End Date |
2000-08-11
|
Activity |
REGULAR INSPECTION
|
Number Inspectors |
1
|
Total Hours |
19
|
|
|
McCarthy Pit (Austin Construction)
|
Surface
|
Abandoned
|
Construction Sand and Gravel
|
|
Directions to Mine |
In Addison take Rt 417 west, turn left onto south street, cross the bridge and turn left onto Cleveland Drive follow out past school and Gun Club, driveway on right side of Rd.
|
Parties
Name
|
Austin Construction LLC
|
Role
|
Operator
|
Start Date
|
2006-07-12
|
|
Name
|
Michael Austin
|
Role
|
Current Controller
|
Start Date
|
2006-07-12
|
|
Name
|
Austin Construction LLC
|
Role
|
Current Operator
|
|
Inspections
Start Date |
2010-11-18
|
End Date |
2010-11-18
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
9.25
|
|
Start Date |
2009-09-23
|
End Date |
2009-10-01
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
18
|
|
Start Date |
2009-07-15
|
End Date |
2009-07-15
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
8.75
|
|
Start Date |
2008-05-07
|
End Date |
2008-05-07
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
10.25
|
|
Start Date |
2006-10-17
|
End Date |
2006-10-19
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
10
|
|
Start Date |
2006-07-12
|
End Date |
2006-07-13
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
14
|
|
Productions
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2014
|
Annual Hours
|
1
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
1
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2013
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2012
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2011
|
Annual Hours
|
20
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
20
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2011
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2010
|
Annual Hours
|
2419
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
1210
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2010
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2009
|
Annual Hours
|
1134
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
1134
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2009
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2008
|
Annual Hours
|
2227
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
1114
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2008
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2007
|
Annual Hours
|
1341
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
1341
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2007
|
Annual Hours
|
5
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
5
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2006
|
Annual Hours
|
1690
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
1690
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2006
|
Annual Hours
|
3
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
3
|
|
|
Route 125 Pit
|
Surface
|
Intermittent
|
Construction Sand and Gravel
|
|
Directions to Mine |
The facility is located on the east side of County Route 125 approximately 1.5 miles north of the intersection of Route 333 and Route 125 in Campbell.
|
Parties
Name
|
Austin Construction, LLC
|
Role
|
Operator
|
Start Date
|
2010-11-01
|
|
Name
|
Michael Austin
|
Role
|
Current Controller
|
Start Date
|
2010-11-01
|
|
Name
|
Austin Construction, LLC
|
Role
|
Current Operator
|
|
Inspections
Start Date |
2024-09-16
|
End Date |
2024-09-16
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
3
|
|
Start Date |
2024-09-05
|
End Date |
2024-09-06
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
13.5
|
|
Start Date |
2023-06-14
|
End Date |
2023-06-21
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
17.5
|
|
Start Date |
2022-09-13
|
End Date |
2022-09-13
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
1.5
|
|
Start Date |
2022-08-30
|
End Date |
2022-08-30
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
3.75
|
|
Start Date |
2022-08-16
|
End Date |
2022-08-17
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
11
|
|
Start Date |
2021-07-28
|
End Date |
2021-07-28
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
10.5
|
|
Start Date |
2021-07-21
|
End Date |
2021-07-22
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
17
|
|
Start Date |
2019-11-05
|
End Date |
2019-11-06
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
10
|
|
Start Date |
2019-07-03
|
End Date |
2019-07-03
|
Activity |
Special Emphasis Programs
|
Number Inspectors |
1
|
Total Hours |
3
|
|
Start Date |
2018-10-17
|
End Date |
2018-10-18
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
13.75
|
|
Start Date |
2018-07-05
|
End Date |
2018-07-06
|
Activity |
Verbal Hazard Complaint Inspections
|
Number Inspectors |
1
|
Total Hours |
7.75
|
|
Start Date |
2017-11-20
|
End Date |
2017-11-20
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
3.75
|
|
Start Date |
2017-11-02
|
End Date |
2017-11-03
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
16.25
|
|
Start Date |
2017-06-26
|
End Date |
2017-06-28
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
22.25
|
|
Start Date |
2016-05-18
|
End Date |
2016-05-19
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
10.75
|
|
Start Date |
2015-05-28
|
End Date |
2015-05-28
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
11.25
|
|
Start Date |
2014-05-22
|
End Date |
2014-05-22
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
11.25
|
|
Start Date |
2012-10-23
|
End Date |
2012-10-24
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
15.5
|
|
Start Date |
2012-03-15
|
End Date |
2012-03-20
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
20.25
|
|
Productions
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2024
|
Annual Hours
|
1871
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
3
|
Avg. Employee Hours
|
624
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2023
|
Annual Hours
|
1689
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
3
|
Avg. Employee Hours
|
563
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2022
|
Annual Hours
|
4317
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
3
|
Avg. Employee Hours
|
1439
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2021
|
Annual Hours
|
4147
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
3
|
Avg. Employee Hours
|
1382
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2020
|
Annual Hours
|
6281
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
5
|
Avg. Employee Hours
|
1256
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2019
|
Annual Hours
|
5981
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
5
|
Avg. Employee Hours
|
1196
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2018
|
Annual Hours
|
6592
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
4
|
Avg. Employee Hours
|
1648
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2017
|
Annual Hours
|
6746
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
5
|
Avg. Employee Hours
|
1349
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2016
|
Annual Hours
|
6887
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
5
|
Avg. Employee Hours
|
1377
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2016
|
Annual Hours
|
1
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
1
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2015
|
Annual Hours
|
5800
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
4
|
Avg. Employee Hours
|
1450
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2015
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2014
|
Annual Hours
|
5096
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
4
|
Avg. Employee Hours
|
1274
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2014
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2013
|
Annual Hours
|
4123
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
4
|
Avg. Employee Hours
|
1031
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2013
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2012
|
Annual Hours
|
12395
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
6
|
Avg. Employee Hours
|
2066
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2012
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2011
|
Annual Hours
|
9681
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
5
|
Avg. Employee Hours
|
1936
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2011
|
Annual Hours
|
4
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
4
|
|
|
Metso ST272
|
Surface
|
Abandoned
|
Construction Sand and Gravel
|
|
Directions to Mine |
Portable - will notify Office @ 5054 County Rt 125 Campbell, NY
|
Parties
Name
|
Austin Construction LLC
|
Role
|
Operator
|
Start Date
|
2012-03-12
|
|
Name
|
Michael Austin
|
Role
|
Current Controller
|
Start Date
|
2012-03-12
|
|
Name
|
Austin Construction LLC
|
Role
|
Current Operator
|
|
Inspections
Start Date |
2013-05-14
|
End Date |
2013-05-14
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
3.25
|
|
Start Date |
2013-02-20
|
End Date |
2013-02-20
|
Activity |
Mine Idle Activity
|
Number Inspectors |
2
|
Total Hours |
4
|
|
Start Date |
2012-08-15
|
End Date |
2012-08-21
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
10.25
|
|
Productions
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2013
|
Annual Hours
|
1016
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
508
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2013
|
Annual Hours
|
3
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
3
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2012
|
Annual Hours
|
514
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
5
|
Avg. Employee Hours
|
103
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2012
|
Annual Hours
|
3
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
3
|
|
|