Name: | BURGESS STEEL ERECTORS OF NEW YORK, LLC |
Jurisdiction: | New York |
Legal type: | DOMESTIC LIMITED LIABILITY COMPANY |
Status: | Active |
Date of registration: | 18 Oct 2007 (17 years ago) |
Entity Number: | 3581894 |
ZIP code: | 10281 |
County: | New York |
Place of Formation: | New York |
Address: | MDMC, LLP, 225 LIBERTY STREET, 36TH FLOOR, NEW YORK, NY, United States, 10281 |
Name | Role | Address |
---|---|---|
DAVID M. ALBERTS, ESQ. | Agent | 225 LIBERTY STREET, 36TH FLOOR, NEW YORK, NY, 10281 |
Name | Role | Address |
---|---|---|
DAVID M. ALBERTS, ESQ. | DOS Process Agent | MDMC, LLP, 225 LIBERTY STREET, 36TH FLOOR, NEW YORK, NY, United States, 10281 |
Start date | End date | Type | Value |
---|---|---|---|
2020-06-17 | 2024-06-12 | Address | 225 LIBERTY STREET, 36TH FLOOR, NEW YORK, NY, 10281, USA (Type of address: Registered Agent) |
2020-06-17 | 2024-06-12 | Address | MDMC, LLP, 225 LIBERTY STREET, 36TH FLOOR, NEW YORK, NY, 10281, USA (Type of address: Service of Process) |
2011-11-29 | 2020-06-17 | Address | 301 N MAIN ST, STE 4, NEW CITY, NY, 10956, USA (Type of address: Service of Process) |
2009-10-16 | 2011-11-29 | Address | ATTN: RICHARD A. KATZ, 228 EAST 45TH STREET, 17TH FL, NEW YORK, NY, 10017, USA (Type of address: Service of Process) |
2007-10-18 | 2009-10-16 | Address | ATTN; RICHARD A. KATZ, 228 EAST 45TH STREET, 17TH FL, NEW YORK, NY, 10017, USA (Type of address: Service of Process) |
Filing Number | Date Filed | Type | Effective Date |
---|---|---|---|
240612003271 | 2024-06-12 | BIENNIAL STATEMENT | 2024-06-12 |
200617000514 | 2020-06-17 | CERTIFICATE OF CHANGE | 2020-06-17 |
131107002066 | 2013-11-07 | BIENNIAL STATEMENT | 2013-10-01 |
111129002284 | 2011-11-29 | BIENNIAL STATEMENT | 2011-10-01 |
091016002015 | 2009-10-16 | BIENNIAL STATEMENT | 2009-10-01 |
080205000833 | 2008-02-05 | CERTIFICATE OF PUBLICATION | 2008-02-05 |
071018000230 | 2007-10-18 | ARTICLES OF ORGANIZATION | 2007-10-18 |
Inspection Nr | Report ID | Date Opened | Site Address | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
341747939 | 0215000 | 2016-08-29 | 550 5TH AVE., NEW YORK, NY, 10036 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Type | Inspection |
Activity Nr | 1174745 |
Safety | Yes |
Violation Items
Citation ID | 01001 |
Citaton Type | Other |
Standard Cited | 19260502 D16 III |
Issuance Date | 2017-02-21 |
Abatement Due Date | 2017-03-03 |
Current Penalty | 8149.0 |
Initial Penalty | 8149.0 |
Final Order | 2017-03-21 |
Nr Instances | 1 |
Nr Exposed | 1 |
Related Event Code (REC) | Referral |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1926.502(d)(16)(iii): Personal fall arrest systems, when stopping a fall, were not rigged such that an employee could not free fall more than 6 feet (1.8 m) nor contact any lower level: a) 5th floor, west side elevator shaft addition structural steel: An employee fell and hit the work deck below while utilizing a fall arrest system. The fall arrest system was not rigged such that the employee could not contact any lower level. On or about 08/27/16. |
Citation ID | 01002 |
Citaton Type | Serious |
Standard Cited | 19260754 A |
Issuance Date | 2017-02-21 |
Abatement Due Date | 2017-03-03 |
Current Penalty | 6519.0 |
Initial Penalty | 8149.0 |
Final Order | 2017-03-21 |
Nr Instances | 1 |
Nr Exposed | 3 |
Related Event Code (REC) | Referral |
Gravity | 5 |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1926.754(a): Structural stability was not maintained at all times during the erection process. a) 5th floor, west side elevator shaft addition structural steel: A lateral steel beam broke off from a steel column and fell while employees were erecting structural steel for a new elevator shaft addition. Structural stability was not maintained at all times during the erection process. On or about 08/27/16. |
Date of last update: 10 Mar 2025