346686306
|
0215800
|
2023-05-08
|
8436 SLIVER SPRUCE CIRCLE, LIVERPOOL, NY, 13090
|
|
Inspection Type |
Complaint
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2023-05-08
|
Emphasis |
L: FALL
|
Related Activity
Type |
Inspection |
Activity Nr |
1668724 |
Safety |
Yes |
|
Type |
Complaint |
Activity Nr |
2028728 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Repeat |
Standard Cited |
19260501 B13 |
Issuance Date |
2023-10-30 |
Current Penalty |
12500.0 |
Initial Penalty |
12500.0 |
Final Order |
2023-12-27 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b): a) At the worksite, 8436 Silver Spruce Circle, Liverpool, NY 13090. On or about May 8, 2023, an employee was engaged in residential roofing activities on a roof with a 6:12 pitch, approximately 15 feet from eave to ground. The employee was not protected from falling by use of guardrail systems, safety net systems, or a personal fall arrest system. J. Lindsley Roofing, LLC was previously cited for a violation of this occupational safety and health standard or its equivalent standard (1926.501(b)(13)), which was contained in OSHA inspection number 1615549, citation number 1, item number 1and was affirmed as a final order on (12-19-2022), with respect to a workplace located at 198 Balsam Street, Liverpool, NY 13088. |
|
|
346155492
|
0215800
|
2022-08-18
|
198 BALSAM STREET, LIVERPOOL, NY, 13088
|
|
Inspection Type |
Prog Other
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2022-08-18
|
Emphasis |
L: FALL
|
Case Closed |
2023-03-29
|
Related Activity
Type |
Inspection |
Activity Nr |
1634126 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260501 B13 |
Issuance Date |
2022-12-05 |
Current Penalty |
2900.0 |
Initial Penalty |
4144.0 |
Final Order |
2022-12-19 |
Nr Instances |
1 |
Nr Exposed |
6 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.501(b)(13):Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b): a) 198 Balsam Street, Liverpool, NY 13088: On or about August 18, 2022, employer failed to provide employees engaged in residential roofing activities on a 2-story house with guardrail systems, safety net system, or personal fall arrest system, nor were employees provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b). |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19261053 B01 |
Issuance Date |
2022-12-05 |
Current Penalty |
2900.0 |
Initial Penalty |
4144.0 |
Final Order |
2022-12-19 |
Nr Instances |
1 |
Nr Exposed |
6 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.1053(b)(1): Where portable ladders were used for access to an upper landing surface and the ladder's length allows, the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface being accessed: a) 198 Balsam Street, Liverpool, NY 13088: On or about August 18, 2022, employees were accessing the roof of a 2 story house, to perform residential roofing activities, using a ladder a ladder that had side rails that did not extend 3 feet beyond the access point. |
|
|
340019967
|
0215800
|
2014-10-17
|
178 EDGEHILL RD, SYRACUSE, NY, 13224
|
|
Inspection Type |
Complaint
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2014-10-17
|
Emphasis |
L: FALL
|
Case Closed |
2018-11-27
|
Related Activity
Type |
Complaint |
Activity Nr |
915465 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001A |
Citaton Type |
Serious |
Standard Cited |
19260416 A01 |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-11 |
Current Penalty |
500.0 |
Initial Penalty |
2200.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
1 |
Nr Exposed |
3 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.416(a)(1): Employees were permitted to work in proximity to electric power circuits and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means: a) Front of Structure at main electrical service entrance, On or about 10/17/14: Employees were working within three feet of the 240 service entrance. An aluminum rain gutter was laying across the energized conductors at the entrance to the structure. Abatement certification is required for this item. |
|
Citation ID |
01001B |
Citaton Type |
Serious |
Standard Cited |
19260451 F06 |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-09 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
1 |
Nr Exposed |
3 |
Related Event Code (REC) |
Complaint |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(f)(6): Scaffolds were erected, used, dismantled, altered, or moved such that they, or any conductive material handled on them, could have come closer than the minimum distances established for specific voltages as set forth in the table in subparagraph (f)(6): a) Front of Structure at main electrical service entrance, On or about 10/17/2014: A metal ladder jack bracket/platform approximately 16 feet in elevation was erected within 3 feet of the structures 240 volt main electrical service entrance. Abatement certification is required for this item. |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19260451 B05 II |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-11 |
Current Penalty |
500.0 |
Initial Penalty |
2200.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
2 |
Nr Exposed |
4 |
Related Event Code (REC) |
Complaint |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(b)(5)(ii): The end of a platform greater than 10 feet in length extended over its support more than 18 inches and the platform was not designed and installed so that the cantilevered portion of the platform is able to support employees without tipping, or has guardrails which block employee access to the cantilevered end: a) Front of Roof, On or about 10/17/14: Employees were working on a roof jack platform which had sides extending over four feet past its end support. Employees were exposed to fall hazards of over 20 feet. b) Side of Roof, On or about 10/17/2014: Employees were working off of a ladder jack scaffold platform which had sides extending over four feet past both of its end supports. Abatement certification is required for this item. |
|
Citation ID |
01003 |
Citaton Type |
Serious |
Standard Cited |
19260451 E01 |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-11 |
Current Penalty |
500.0 |
Initial Penalty |
2200.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
2 |
Nr Exposed |
4 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface were not used: a) Front of Roof, On or about 10/17/14: Employees were accessing the ladder jack scaffold platform utilizing the supporting ladder which required the employees to climb over the platform they were accessing/ egressing. Employees were exposed to fall hazards of 18 feet. b) Side of Roof, On or about 10/17/2014: Employees were accessing the ladder jack platform utilizing the supporting ladder which required the employees to climb over the platform they were accessing/ egressing. Employees exposed to falls of 12 feet. Abatement certification is required for this item. |
|
Citation ID |
01004A |
Citaton Type |
Serious |
Standard Cited |
19260452 N01 |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-11 |
Current Penalty |
500.0 |
Initial Penalty |
2200.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.452(n)(1): Scaffold platforms were placed higher than the second highest rung of the supporting ladder: a) Side of Roof, On or about 10/17/2014: Employees were working off of a scaffold platform which was supported by the top rung of an extension ladder. Abatement certification is required for this item. |
|
Citation ID |
01004B |
Citaton Type |
Serious |
Standard Cited |
19260452 N03 |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-11 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.452(n)(3): 29 CFR 1926.452(n)(3) : Ladders used to support step, platform, and trestle ladder scaffolds were not placed, fastened, or equipped with devices to prevent slipping. a) Side of Roof, On or about 10/17/2014: Employees were working off of a scaffold platform which was supported by an extension ladder which was not secured to prevent slipping. Abatement certification is required for this item. |
|
Citation ID |
02001A |
Citaton Type |
Repeat |
Standard Cited |
19260404 B01 II |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-11 |
Current Penalty |
1000.0 |
Initial Penalty |
4400.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
1 |
Nr Exposed |
9 |
Related Event Code (REC) |
Complaint |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.404(b)(1)(ii): Employer did not use either ground fault circuit interrupters as specified in paragraph (b)(1)(ii) of this section, or an assured equipment grounding conductor program as specified in paragraph (b)(1)(iii) of this section to protect employees on construction sites: a) Worksite- On or about 10/17/14: Employees were utilizing electrical equipment, such as a Dewalt circular saw and a battery charging equipment. There was no ground fault circuit interrupters, or assured equipment grounding conductor program in use. Abatement documentation required for this item. J. Lindsley Roofing, LLC was previously cited for a violation of this occupational safety and health standard or its equivalent standard 1926.404(b)(1)(ii) which was contained in OSHA inspection number 965920, citation number 1, item number 4b and was affirmed as a final order on 5/1/2014, with respect to a workplace located at 1002 State Route 176 Fulton, NY 13069. |
|
Citation ID |
02001B |
Citaton Type |
Repeat |
Standard Cited |
19260404 F06 |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-11 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
1 |
Nr Exposed |
1 |
Related Event Code (REC) |
Complaint |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.404(f)(6): The path to ground from circuits, equipment, or enclosures was not permanent and continuous: a) At the jobsite, On or about 10/17/14: A Dewalt circular saw was used without a continuous path to ground. Abatement documentation required for this item. J. Lindsley Roofing, LLC was previously cited for a violation of this occupational safety and health standard or its equivalent standard 1926.404(f)(6) which was contained in OSHA inspection number 965920, citation number 1, item number 4c and was affirmed as a final order on 5/1/2014, with respect to a workplace located at 1002 State Route 176 Fulton, NY 13069. |
|
Citation ID |
02002 |
Citaton Type |
Repeat |
Standard Cited |
19260501 B13 |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-11 |
Current Penalty |
1000.0 |
Initial Penalty |
4400.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
1 |
Nr Exposed |
3 |
Related Event Code (REC) |
Complaint |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b): a) Roof, On or about 10/17/14: Employees were working on a high pitched residential roof with out utilizing any fall protection. Employees were exposed to falls of over 18 feet. Abatement documentation is required for this item. J. Lindsley Roofing, LLC was previously cited for a violation of this occupational safety and health standard or its equivalent standard 1926.501(b)(10), which was contained in OSHA inspection number 965920, citation number 1, item number 3a and was affirmed as a final order on 5/1/2014, with respect to a workplace located at 1002 State Route 176 Fulton, NY 13069. |
|
Citation ID |
02003 |
Citaton Type |
Repeat |
Standard Cited |
19261053 B01 |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-11 |
Current Penalty |
1000.0 |
Initial Penalty |
4400.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
2 |
Nr Exposed |
4 |
Related Event Code (REC) |
Complaint |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.1053(b)(1): Where portable ladders were used for access to an upper landing surface and the ladder's length allows, the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface being accessed: a) Front of Roof, On or about 10/17/14: Employees were accessing the roof from a ladder jack scaffold platform. The ladder did not extend three feet past the eave. Employees were exposed to fall hazards of 18 feet. b) Side of Roof, On or about 10/17/2014: Employees were accessing the roof from a ladder jack/ supported scaffold platform. The ladder did not extend past the eave. Employees exposed to falls of 12 feet. Abatement documentation is required for this item. J. Lindsley Roofing, LLC was previously cited for a violation of this occupational safety and health standard or its equivalent standard 1926.1053(b)(1), which was contained in OSHA inspection number 965920, citation number 1, item number 3b and was affirmed as a final order on 5/1/2014, with respect to a workplace located at 1002 State Route 176 Fulton, NY 13069. |
|
Citation ID |
03001 |
Citaton Type |
Other |
Standard Cited |
19260503 B01 |
Issuance Date |
2014-12-01 |
Abatement Due Date |
2014-12-14 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Contest Date |
2014-12-10 |
Final Order |
2015-06-11 |
Nr Instances |
1 |
Nr Exposed |
9 |
Related Event Code (REC) |
Complaint |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.503(b)(1): The employer did not verify compliance with paragraph (a) of this section by preparing a written (training) certification record including the name or other identity of the employee trained, the date(s) of the training, and the signature of the person who conducted the training or the signature of the employer. a) At the jobsite, On or about 10/17/2014: Employees were exposed to fall hazards. The company had not documented/ certified any fall protection training for employees. Abatement certification required for this item. |
|
Citation ID |
04001 |
Citaton Type |
Other |
Standard Cited |
19030019 C01 |
Issuance Date |
2015-09-09 |
Abatement Due Date |
2015-09-28 |
Current Penalty |
440.0 |
Initial Penalty |
440.0 |
Final Order |
2015-11-03 |
Nr Instances |
1 |
Nr Exposed |
4 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1903.19(c)(1): The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated: a) At the jobsite, on or about 9/9/2015: The employer did not provide abatement certification for Citation 01, Items 001a, 001b, 002, 003, 004a 004b, Citation 02, Items 001a, 001b, 002, 003 and Citation 03, Item 001 issued on December 1, 2015. An abatement demand letter was sent to the employer on August 3, 2015. Abatement certification is required for this item. |
|
|
339659203
|
0215800
|
2014-04-02
|
STAR NAIL SALON, 109 EAST BROADWAY, FULTON, NY, 13069
|
|
Inspection Type |
Complaint
|
Scope |
Complete
|
Safety/Health |
Safety
|
Close Conference |
2014-04-02
|
Emphasis |
L: FALL
|
Case Closed |
2019-02-28
|
Related Activity
Type |
Complaint |
Activity Nr |
879249 |
Safety |
Yes |
Health |
Yes |
|
Violation Items
Citation ID |
01001A |
Citaton Type |
Serious |
Standard Cited |
19260028 A |
Issuance Date |
2014-04-18 |
Abatement Due Date |
2014-04-28 |
Current Penalty |
1120.0 |
Initial Penalty |
1600.0 |
Final Order |
2014-05-01 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.28(a): The employer did not require the wearing of appropriate personal protective equipment in all operations where there is an exposure to hazardous conditions: a) Entire roof, on or about 4-2-14: Five employees were working with adhesives, mastics, and sealants, without the PPE required to protect hands and exposed skin. |
|
Citation ID |
01001B |
Citaton Type |
Serious |
Standard Cited |
19260059 |
Issuance Date |
2014-04-18 |
Abatement Due Date |
2014-04-28 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2014-05-01 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.59: 29 CFR 1926.59: An employer engaged in construction activities did not comply with the requirements set forth in Part 1910, Section 1200, Hazard Communication: a) Entire worksite, on or about 4-2-14: Five employees were working with adhesives, mastics, and sealants, without a hazard communication program or MSDS sheets available. |
|
Citation ID |
01001C |
Citaton Type |
Serious |
Standard Cited |
19260102 A01 |
Issuance Date |
2014-04-18 |
Abatement Due Date |
2014-04-28 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2014-05-01 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.102(a)(1): Eye and face protective equipment were not used when machines or operations presented potential eye or face injury from physical, chemical, or radiation agents: a) Entire roof, on or about 4-2-14: Five employees were working with adhesives, mastics, and sealants, without eye protection. |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19260150 C01 VI |
Issuance Date |
2014-04-18 |
Abatement Due Date |
2014-04-28 |
Current Penalty |
0.0 |
Initial Penalty |
2000.0 |
Final Order |
2014-05-01 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.150(c)(1)(vi): A fire extinguisher, rated not less than 10B, was not provided within 50 feet of wherever more than 5 gallons of flammable or combustible liquids or 5 pounds of flammable gas were being used on the jobsite: a) Entire roof, on or about 4-2-14: Five employees were using flammable liquids (adhesive) while working on a roof, without a fire extinguisher. |
|
Citation ID |
01003A |
Citaton Type |
Serious |
Standard Cited |
19260501 B10 |
Issuance Date |
2014-04-18 |
Abatement Due Date |
2014-04-28 |
Current Penalty |
1400.0 |
Initial Penalty |
2000.0 |
Final Order |
2014-05-01 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.501(b)(10): Each employee engaged in roofing activities on low-slope roofs with unprotected sides and edges 6 feet or more above lower levels, was not protected from falling by guardrail systems, safety net systems, personal fall arrest systems, or a combination of warning line system and guardrail system, warning line system and safety net system, or warning line system and personal fall arrest system, or warning line system and safety monitoring system. Or, on roofs 50-feet (15.25 m) or less in width, each employee was not protected by use of a monitoring system: a) Entire roof, on or about 4-2-14: Five employees were working on a flat roof and were not protected from falls, exposing the employees to a fall hazard of 20 feet 6 inches. |
|
Citation ID |
01003B |
Citaton Type |
Serious |
Standard Cited |
19261053 B01 |
Issuance Date |
2014-04-18 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2014-05-01 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.1053(b)(1): Portable ladders were used for access to an upper landing surface and the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface to which the ladder was used to gain access: a) West side of building, on or about 4-2-14: Employees were accessing the roof via an extension ladder that was extended 25 inches above the landing surface, exposing the employees to a fall hazard of 9 feet. |
|
Citation ID |
01004A |
Citaton Type |
Other |
Standard Cited |
19260403 B02 |
Issuance Date |
2014-04-18 |
Current Penalty |
0.0 |
Initial Penalty |
1600.0 |
Final Order |
2014-05-01 |
Nr Instances |
2 |
Nr Exposed |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.403(b)(2): Listed, labeled, or certified equipment was not installed and used in accordance with instructions included in the listing, labeling, or certification: a) Northwest side of building, on or about 4-2-14: Employees were operating power tools and equipment that were plugged into a relocatable power tap (RPT) that was not being used in accordance with the manufacturers recommendations or as listed and labeled. b) North side of building, inside, on or about 4-2-14: Employees were operating power tools and equipment that were plugged into a relocatable power tap (RPT) that was not being used in accordance with the manufacturers recommendations or as listed and labeled. |
|
Citation ID |
01004B |
Citaton Type |
Serious |
Standard Cited |
19260404 B01 II |
Issuance Date |
2014-04-18 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2014-05-01 |
Nr Instances |
2 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.404(b)(1)(ii): On a construction site, where an assured equipment grounding program was not utilized, all 120-volt, single-phase, 15 and 20 ampere receptacle outlets which were not a part of the permanent wiring of the building or structure and which are in use by employees did not have approved ground fault circuit interrupters for personal protection: a) Northwest side of building, on or about 4-2-14: Employees were operating power tools and equipment that were powered through a receptacle that was not protected by a ground fault circuit interrupter (GFCI). b) North side of building, inside, on or about 4-2-14: Employees were operating power tools and equipment that were powered through a receptacle that was not protected by a ground fault circuit interrupter (GFCI). |
|
Citation ID |
01004C |
Citaton Type |
Serious |
Standard Cited |
19260404 F06 |
Issuance Date |
2014-04-18 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2014-05-01 |
Nr Instances |
2 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.404(f)(6): The path to ground from circuits, equipment, or enclosures was not permanent and continuous: a) Northwest corner of building, on or about 4-2-14: Employees were operating power tools and equipment that were plugged into two cords that did not have a continuous path to ground due to missing ground pins. |
|
|
309384766
|
0215800
|
2006-11-17
|
RTE 48, FULTON, NY, 13069
|
|
Inspection Type |
Referral
|
Scope |
Partial
|
Safety/Health |
Health
|
Close Conference |
2006-12-21
|
Emphasis |
L: FALL
|
Case Closed |
2008-08-25
|
Related Activity
Type |
Referral |
Activity Nr |
200886141 |
Safety |
Yes |
Health |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260416 E01 |
Issuance Date |
2007-01-09 |
Abatement Due Date |
2007-01-12 |
Current Penalty |
600.0 |
Initial Penalty |
600.0 |
Nr Instances |
1 |
Nr Exposed |
3 |
Gravity |
02 |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19260602 C01 VII |
Issuance Date |
2007-01-09 |
Abatement Due Date |
2007-01-27 |
Current Penalty |
600.0 |
Initial Penalty |
600.0 |
Nr Instances |
1 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
02 |
|
Citation ID |
02001A |
Citaton Type |
Other |
Standard Cited |
19101200 E01 |
Issuance Date |
2007-01-09 |
Abatement Due Date |
2007-02-11 |
Nr Instances |
1 |
Nr Exposed |
4 |
Related Event Code (REC) |
Referral |
Gravity |
02 |
|
Citation ID |
02001B |
Citaton Type |
Serious |
Standard Cited |
19101200 G01 |
Issuance Date |
2007-01-09 |
Abatement Due Date |
2007-02-11 |
Nr Instances |
1 |
Nr Exposed |
4 |
Gravity |
02 |
|
Citation ID |
02001C |
Citaton Type |
Other |
Standard Cited |
19101200 H01 |
Issuance Date |
2007-01-09 |
Abatement Due Date |
2007-02-11 |
Nr Instances |
1 |
Nr Exposed |
4 |
Gravity |
02 |
|
|