Directions to Mine |
Portable Plant Check 56.1000 - Last reported at 7289 US-4, Fort Ann, NY
|
Parties
Name
|
Mohican Quarries
|
Role
|
Operator
|
Start Date
|
2010-07-01
|
|
Name
|
Danna Jay Ellsworth; Ruben Walter Ellsworth
|
Role
|
Current Controller
|
Start Date
|
2010-07-01
|
|
Name
|
Mohican Quarries
|
Role
|
Current Operator
|
|
Inspections
Start Date |
2024-05-22
|
End Date |
2024-05-22
|
Activity |
Special Emphasis Programs
|
Number Inspectors |
1
|
Total Hours |
1
|
|
Start Date |
2024-03-21
|
End Date |
2024-03-22
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
20.75
|
|
Start Date |
2023-10-11
|
End Date |
2023-10-12
|
Activity |
Spot Inspection
|
Number Inspectors |
1
|
Total Hours |
4
|
|
Start Date |
2023-05-17
|
End Date |
2023-05-17
|
Activity |
Special Emphasis Programs
|
Number Inspectors |
1
|
Total Hours |
.75
|
|
Start Date |
2023-02-14
|
End Date |
2023-02-16
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
25.25
|
|
Start Date |
2022-06-27
|
End Date |
2022-06-30
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
4.5
|
|
Start Date |
2020-10-01
|
End Date |
2020-10-08
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
3.75
|
|
Start Date |
2020-04-14
|
End Date |
2020-04-17
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
11
|
|
Start Date |
2019-04-24
|
End Date |
2019-05-02
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
8
|
|
Start Date |
2018-05-29
|
End Date |
2018-06-07
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
18.5
|
|
Start Date |
2016-10-19
|
End Date |
2016-10-19
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
3.25
|
|
Start Date |
2016-10-06
|
End Date |
2016-10-12
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
12.5
|
|
Start Date |
2016-06-14
|
End Date |
2016-06-15
|
Activity |
Spot Inspection
|
Number Inspectors |
1
|
Total Hours |
9.75
|
|
Start Date |
2016-04-18
|
End Date |
2016-04-21
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
6.5
|
|
Start Date |
2016-04-12
|
End Date |
2016-04-14
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
14
|
|
Start Date |
2015-10-14
|
End Date |
2015-10-14
|
Activity |
Special Emphasis Programs
|
Number Inspectors |
1
|
Total Hours |
.75
|
|
Start Date |
2015-05-26
|
End Date |
2015-06-01
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
15.75
|
|
Start Date |
2014-06-03
|
End Date |
2014-06-09
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
26.25
|
|
Start Date |
2012-10-30
|
End Date |
2012-10-31
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
9
|
|
Start Date |
2011-10-05
|
End Date |
2011-10-06
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
9.5
|
|
Productions
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2024
|
Annual Hours
|
615
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
308
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2024
|
Annual Hours
|
20
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
20
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2023
|
Annual Hours
|
913
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
457
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2023
|
Annual Hours
|
29
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
29
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2022
|
Annual Hours
|
428
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
214
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2022
|
Annual Hours
|
24
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
24
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2021
|
Annual Hours
|
342
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
171
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2021
|
Annual Hours
|
24
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
24
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2020
|
Annual Hours
|
374
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
187
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2020
|
Annual Hours
|
32
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
32
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2019
|
Annual Hours
|
318
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
159
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2019
|
Annual Hours
|
40
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
40
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2018
|
Annual Hours
|
215
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
108
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2018
|
Annual Hours
|
38
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
38
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2017
|
Annual Hours
|
442
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
221
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2017
|
Annual Hours
|
65
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
65
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2016
|
Annual Hours
|
1617
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
809
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2016
|
Annual Hours
|
146
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
146
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2015
|
Annual Hours
|
2272
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
1136
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2015
|
Annual Hours
|
563
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
563
|
|
|
Directions to Mine |
From Albany take I87 North to Exit 20. Left on Route 9 North to a right onto Route 149 East into the Village of Fort Ann. Head North on Route 4 for approximately 3 miles, building will be on left hand side of road.
|
Parties
Name
|
Mohican Quarries
|
Role
|
Operator
|
Start Date
|
2017-09-01
|
|
Name
|
Danna Jay Ellsworth; Ruben Walter Ellsworth
|
Role
|
Current Controller
|
Start Date
|
2017-09-01
|
|
Name
|
Mohican Quarries
|
Role
|
Current Operator
|
|
Inspections
Start Date |
2019-07-22
|
End Date |
2019-07-25
|
Activity |
Mine Idle Activity
|
Number Inspectors |
1
|
Total Hours |
6.75
|
|
Start Date |
2017-11-03
|
End Date |
2017-11-03
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
4
|
|
Start Date |
2017-10-17
|
End Date |
2017-10-31
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
7
|
|
Start Date |
2017-10-11
|
End Date |
2017-10-16
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
15
|
|
Productions
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2018
|
Annual Hours
|
545
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
273
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2018
|
Annual Hours
|
16
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
16
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2017
|
Annual Hours
|
1997
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
3
|
Avg. Employee Hours
|
666
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2017
|
Annual Hours
|
64
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
64
|
|
|