Search icon

WAYNE'S STUCCO & PLASTER, LLC

Company Details

Name: WAYNE'S STUCCO & PLASTER, LLC
Jurisdiction: New York
Legal type: DOMESTIC LIMITED LIABILITY COMPANY
Status: Inactive
Date of registration: 15 Apr 2014 (11 years ago)
Date of dissolution: 15 Aug 2019
Entity Number: 4561786
ZIP code: 13158
County: Cortland
Place of Formation: New York
Address: 3944 ROUTE 13, TRUXTON, NY, United States, 13158

DOS Process Agent

Name Role Address
THE LLC DOS Process Agent 3944 ROUTE 13, TRUXTON, NY, United States, 13158

Filings

Filing Number Date Filed Type Effective Date
190815000646 2019-08-15 ARTICLES OF DISSOLUTION 2019-08-15
140415010003 2014-04-15 ARTICLES OF ORGANIZATION 2014-04-15

OSHA's Inspections within Industry

Inspection Nr Report ID Date Opened Site Address
340011634 0215800 2014-10-14 107 SOUTH MAIN STREET, NORTH SYRACUSE, NY, 13212
Inspection Type Prog Related
Scope Complete
Safety/Health Safety
Close Conference 2014-10-14
Emphasis L: LOCALTARG, P: LOCALTARG
Case Closed 2014-12-16

Related Activity

Type Inspection
Activity Nr 1000762
Safety Yes

Violation Items

Citation ID 01001
Citaton Type Serious
Standard Cited 19260451 B01
Issuance Date 2014-12-08
Abatement Due Date 2014-12-16
Current Penalty 1120.0
Initial Penalty 1600.0
Final Order 2014-12-12
Nr Instances 1
Nr Exposed 2
Gravity 5
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii): a) South side of building, on or about 10-15-14: Two employees were performing plastering tasks while working on scaffold platforms that were not fully planked, exposing the employees to a fall hazard of 9 feet. ABATEMENT CERTIFICATION IS REQUIRED FOR THIS ITEM
Citation ID 02001A
Citaton Type Other
Standard Cited 19261053 B01
Issuance Date 2014-12-08
Abatement Due Date 2014-12-16
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2014-12-12
Nr Instances 1
Nr Exposed 2
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1053(b)(1): Where portable ladders were used for access to an upper landing surface and the ladder's length allows, the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface being accessed: a) South side of building, on or about 10-15-14: Two employees were accessing a scaffold platform via a step ladder that was 4 inches above the landing surface, exposing the employees to a fall hazard of 8 feet. ABATEMENT CERTIFICATION IS REQUIRED FOR THIS ITEM
Citation ID 02001B
Citaton Type Other
Standard Cited 19261053 B13
Issuance Date 2014-12-08
Abatement Due Date 2014-12-16
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2014-12-12
Nr Instances 1
Nr Exposed 2
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1053(b)(13): The top or top step of a stepladder was used as a step: a) South side of building, on or about 10-15-14: Two employees were accessing a scaffold platform while using the top step and top platform of the ladder, exposing the employees to a fall hazard of 8 feet. ABATEMENT CERTIFICATION IS REQUIRED FOR THIS ITEM
338945918 0215800 2013-03-07 PARTY CITY, 2309 N. TRIPHAMMER ROAD, ITHACA, NY, 14850
Inspection Type Complaint
Scope Complete
Safety/Health Safety
Close Conference 2013-03-07
Emphasis L: FALL
Case Closed 2013-04-11

Related Activity

Type Complaint
Activity Nr 808381
Safety Yes
Type Inspection
Activity Nr 894621
Safety Yes

Violation Items

Citation ID 01001
Citaton Type Serious
Standard Cited 19260404 B01 II
Issuance Date 2013-03-25
Current Penalty 840.0
Initial Penalty 1200.0
Final Order 2013-04-02
Nr Instances 1
Nr Exposed 1
Gravity 1
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.404(b)(1)(ii): On a construction site, where an assured equipment grounding program was not utilized, all 120-volt, single-phase, 15 and 20 ampere receptacle outlets which were not a part of the permanent wiring of the building or structure and which are in use by employees did not have approved ground fault circuit interrupers for personal protection: a) South side of building, front, on or about 3-7-13: One employee was operating a drill/mixer that was powered through a cord/receptacle that was not protected by a ground fault circuit interrupter (GFCI).
Citation ID 01002A
Citaton Type Serious
Standard Cited 19260451 B01
Issuance Date 2013-03-25
Abatement Due Date 2013-04-07
Current Penalty 1400.0
Initial Penalty 2000.0
Final Order 2013-04-02
Nr Instances 1
Nr Exposed 1
Gravity 5
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.451(b)(1): Platform(s) on all working levels of scaffolds, were not fully planked or decked between the front uprights and guardrail supports: a) South side of building, front, on or about 3-7-13: one employee was working on a scaffold platform that was not fully planked, exposing the employee to a fall hazard of 13 feet 4 inches.
Citation ID 01002B
Citaton Type Serious
Standard Cited 19260451 E01
Issuance Date 2013-03-25
Abatement Due Date 2013-04-07
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2013-04-02
Nr Instances 2
Nr Exposed 2
Gravity 5
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, sturcture, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access: a) South side of building, front, on or about 3-7-13: Two employees were accessing multiple levels of a scaffold while climbing the x-braces, exposing the employees to a fall hazard of 20 feet 6 inches.
Citation ID 01002C
Citaton Type Serious
Standard Cited 19260451 G01
Issuance Date 2013-03-25
Abatement Due Date 2013-04-07
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2013-04-02
Nr Instances 1
Nr Exposed 2
Gravity 5
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.451(g)(1): Each employee on a scaffold more than 10 feet above a lower level were not protected from falling to that lower level: a) South side of building, front, on or about 3-7-13: Two employees were working an outrigger bracket scaffold platform that did not have a full guardrail system on the ends, exposing the employees to a fall hazard of 20 feet 6 inches.
Citation ID 01002D
Citaton Type Serious
Standard Cited 19260451 G04 XV
Issuance Date 2013-03-25
Abatement Due Date 2013-04-07
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2013-04-02
Nr Instances 1
Nr Exposed 2
Gravity 5
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.451(g)(4)(xv): Crossbracing used in place of a midrail was unacceptable because the crossing point of two braces is between 20 inches (0.5 m) and 30 inches ((0.8 M) above the work platform or as a toprail when the crossing point of two braces is not between 20 inches (0.5 m) and 30 inches (0.8 m) above the work platform or as a toprail when the crossing point of two braces is between 38 inches (0.97 m) and 48 inches (1.3 m) above the work platform. The endpoints at each upright were more than 48 inches (1.3 m) apart: a) South side of building, front, on or about 3-7-13: Two employees were working on a scaffold platform that used cross braces as a full guard rail system, exposing the employee to a fall hazard of 20 feet 6 inches.
Citation ID 02001
Citaton Type Other
Standard Cited 19260100 A
Issuance Date 2013-03-25
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2013-04-02
Nr Instances 1
Nr Exposed 1
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.100(a): Employees working in areas where there was a possible danger of head injury from impact, or falling or flying objects, or from electrical shock and burns, were not protected by protective helmets: a) South side of building, on or about 3-7-13: One employee was working below two others without head protection.

Date of last update: 25 Mar 2025