Inspection Type |
Planned
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2019-12-30
|
Emphasis |
L: LOCALTARG, P: LOCALTARG
|
Case Closed |
2024-03-21
|
Related Activity
Type |
Inspection |
Activity Nr |
1452110 |
Safety |
Yes |
|
Type |
Inspection |
Activity Nr |
1452127 |
Safety |
Yes |
|
Type |
Inspection |
Activity Nr |
1452108 |
Safety |
Yes |
|
Type |
Inspection |
Activity Nr |
1452104 |
Safety |
Yes |
|
Type |
Inspection |
Activity Nr |
1452115 |
Safety |
Yes |
|
Type |
Inspection |
Activity Nr |
1452118 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260451 B01 |
Issuance Date |
2020-06-02 |
Current Penalty |
2313.0 |
Initial Penalty |
2313.0 |
Final Order |
2020-07-01 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii) Location: a) 1st Floor; Main IT room; On first tier of two-tier scaffold On or about 12/18/2019, employees worked from a scaffold and the platform was not fully planked. Employees ere bricklaying. |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19260451 E01 |
Issuance Date |
2020-06-02 |
Current Penalty |
2313.0 |
Initial Penalty |
2313.0 |
Final Order |
2020-07-01 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access. Location: a) 1st Floor; Main IT room; On first tier of two-tier scaffold a) On or about 12/18/2019, employees climbed the scaffold crossbraces and frames to access the working platform to perform masonry bricklaying work. No safe means of access was provided. |
|
|