2022-01-05
|
No data
|
60 STREET, FROM STREET 14 AVENUE TO STREET 15 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb installed.
|
2021-12-20
|
No data
|
63 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb installed in compliance
|
2021-08-06
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb installed
|
2020-10-31
|
No data
|
63 STREET, FROM STREET 19 AVENUE TO STREET 20 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
the curb was installed in compliance
|
2020-08-24
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb installed along with sidewalk flags.
|
2020-07-08
|
No data
|
60 STREET, FROM STREET 14 AVENUE TO STREET 15 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb installed and new sidewalk flags.
|
2020-06-27
|
No data
|
63 STREET, FROM STREET 19 AVENUE TO STREET 20 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk flags and curb installed.
|
2020-06-25
|
No data
|
63 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New sidewalk flags and curb installed.
|
2020-06-04
|
No data
|
21 AVENUE, FROM STREET 58 STREET TO STREET 59 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb ok
|
2020-04-13
|
No data
|
AVENUE T, FROM STREET COLEMAN STREET TO STREET HENDRICKSON STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No materials in the street
|
2020-02-04
|
No data
|
BEDFORD AVENUE, FROM STREET ALBEMARLE ROAD TO STREET TILDEN AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
OCCUPANCY OF SIDEWALK AS STIPULATED, acceptable
|
2020-01-18
|
No data
|
51 STREET, FROM STREET 16 AVENUE TO STREET 17 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Maintain Fence ok
|
2019-12-30
|
No data
|
BEDFORD AVENUE, FROM STREET ALBEMARLE ROAD TO STREET TILDEN AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
no CROSSING SIDEWALK
|
2019-12-03
|
No data
|
51 STREET, FROM STREET 16 AVENUE TO STREET 17 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
the sidewalk is not occupied
|
2019-11-24
|
No data
|
EAST 22 STREET, FROM STREET AVENUE I TO STREET DEAD END
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
FENCE OKAY
|
2019-11-21
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk installed
|
2019-11-21
|
No data
|
62 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
bricks on skids and bags of sand.
|
2019-10-13
|
No data
|
62 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Bricks stored on a skid.
|
2019-10-09
|
No data
|
EAST 22 STREET, FROM STREET AVENUE I TO STREET DEAD END
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
fence okay
|
2019-08-31
|
No data
|
51 STREET, FROM STREET 16 AVENUE TO STREET 17 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Sidewalk occupied
|
2019-08-17
|
No data
|
51 STREET, FROM STREET 15 AVENUE TO STREET 16 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Brand new sidewalk flags installed with gas valve in front of property #1580 in compliance.
|
2019-07-20
|
No data
|
60 STREET, FROM STREET 14 AVENUE TO STREET 15 AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
yellow plastic removed
|
2019-06-24
|
No data
|
63 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
NEW SIDEWALK FLAGS IN FRONT OF PROPERTY, SEALED AND FLUSH
|
2019-06-08
|
No data
|
60 STREET, FROM STREET 14 AVENUE TO STREET 15 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Remove yellow plastic on top of expansion joints between the curb and adjoining property line.
|
2019-03-05
|
No data
|
EAST 22 STREET, FROM STREET AVENUE I TO STREET DEAD END
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Fence maintained on the sidewalk, in front of 929 East 22 Street.
|
2018-12-13
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New sidewalk flags installed, all expansion joints sealed. In front of 1877 59 Street.
|
2018-12-09
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Installation of Curb in Compliance
|
2018-11-09
|
No data
|
51 STREET, FROM STREET 15 AVENUE TO STREET 16 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Maintain fence on the sidewalk i/f/o 1580 51 street
|
2018-10-22
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb repaired, in front of 1877 59 Street.
|
2018-10-11
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New sidewalk flags installed, expansion joints sealed. In front 1877 59 Street.
|
2018-09-13
|
No data
|
62 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No material placed on street at this time
|
2018-09-13
|
No data
|
63 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Fence on sidewalk
|
2018-08-11
|
No data
|
21 AVENUE, FROM STREET 58 STREET TO STREET 59 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
SIDEWALK INSTALLED
|
2018-08-08
|
No data
|
63 STREET, FROM STREET 19 AVENUE TO STREET 20 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
I observed the above respondent/respondent's subcontractor installing 40 feet of a new curb, without a valid DOT permit on file. Expired permit, #B012018177F03 exp. 7/25/2018, used for ID.
|
2018-08-08
|
No data
|
63 STREET, FROM STREET 19 AVENUE TO STREET 20 AVENUE
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
I observed the above respondent/respondent's subcontractor installing 40 feet by 8 feet of a newsidewalk, without a valid DOT permit on file. Expired permit, #B042018177A05 exp. 7/25/2018, used for ID.
|
2018-07-20
|
No data
|
51 STREET, FROM STREET 15 AVENUE TO STREET 16 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Sidewalk Occupied At Time Of Inspection
|
2018-06-13
|
No data
|
63 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
NO material on street at this time.
|
2018-05-26
|
No data
|
JEFFERSON AVENUE, FROM STREET PATCHEN AVENUE TO STREET MALCOLM X BOULEVARD
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
A/T/P/O I OBSERVED THE ABOVE RESPONDENT CLOSED 30 FEET BY 5 FEET OF SIDEWALK AND ROADWAY WITH PLASTIC AND WOOD BARRIERS WITHOUT DOT PERMIT TO DO SO. DOB PERMIT 320942441-01-AL USED FOR I.D.
|
2018-05-03
|
No data
|
62 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No material observed on the street i/f/o 1843 62 street
|
2018-04-25
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No material on the street, at time of inspection.
|
2018-04-02
|
No data
|
63 STREET, FROM STREET 19 AVENUE TO STREET 20 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Crossing of sidewalk not being used, at time of inspection
|
2018-03-28
|
No data
|
JEFFERSON AVENUE, FROM STREET PATCHEN AVENUE TO STREET MALCOLM X BOULEVARD
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
A/T/P/O I observed the above respondent occupying the parking lane in front of their building operation with timber barricades and water-filled jersey barriers. No active DOT permits on file. NYC DOB Permit Number (320942441-01-AL) used to ID.
|
2018-03-24
|
No data
|
21 AVENUE, FROM STREET 58 STREET TO STREET 59 STREET
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
RE-ISSUE CAR WRONG ADDRESS
|
2018-03-24
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
WHITE MARBLE/TILE ON RWY
|
2018-03-10
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Boom truck on roadway in-compliance
|
2018-03-06
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
FENCE IS OK
|
2018-03-03
|
No data
|
62 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No material placed on street at this time
|
2018-03-03
|
No data
|
63 STREET, FROM STREET 19 AVENUE TO STREET 20 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No material placed on street at this time
|
2018-02-27
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Materials are placed in roadway
|
2018-02-27
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
A/T/P/O I observed construction materials (concrete stepping stone) stored in roadway in front of 1875 59 street without permit. Contractor has permit to place material in front of 1877 59 street only. Building permit 320717015-01-AL use for Id
|
2018-02-24
|
No data
|
21 AVENUE, FROM STREET 58 STREET TO STREET 59 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
PLEASE SEAL EXPANSION JOINTS ALONG CURB IN FRONT OF 5810 21ST STREET
|
2018-02-07
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
A/T/P/O I observed construction materials (concrete stepping stone) stored in roadway in front of 1875 59 street without permit. Contractor has permit to place material in front of 1877 59 street only. Building permit 320717015-01-AL use for Id
|
2018-02-07
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Materials (concrete stepping stone) stored in roadway
|
2018-01-12
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Materials stored in r/w.
|
2018-01-11
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Materials are placed in roadway
|
2018-01-08
|
No data
|
51 STREET, FROM STREET 15 AVENUE TO STREET 16 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
FENCE IS OK
|
2017-12-29
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Material stored, cynder blocks on pallets.
|
2017-12-27
|
No data
|
62 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Container on the r/w.
|
2017-12-18
|
No data
|
62 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
NOV issued due to no valid BO@ permit on file to store equipment(refuse container) on roadway
|
2017-12-16
|
No data
|
JEFFERSON AVENUE, FROM STREET PATCHEN AVENUE TO STREET MALCOLM X BOULEVARD
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
Container
|
2017-11-30
|
No data
|
51 STREET, FROM STREET 15 AVENUE TO STREET 16 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No material observed at the construction site i/f/o 1580 51 street
|
2017-11-30
|
No data
|
51 STREET, FROM STREET 15 AVENUE TO STREET 16 AVENUE
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
A/T/P/O I observed the above respondent stored an open construction debris container on the street i/f/o 1580 51 street, without a valid DOT permit on file permit B022017257B21 is used as ID
|
2017-11-02
|
No data
|
JEFFERSON AVENUE, FROM STREET PATCHEN AVENUE TO STREET MALCOLM X BOULEVARD
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
A/T/P/O I OBSERVED THE ABOVE RESPONDENT STORED CONSTRUCTION CONTAINER ON ROADWAY WITHOUT PERMIT TO DO SO. DOB PERMIT 320942441-01-EQ-FN USED FOR I.D.
|
2017-10-29
|
No data
|
VILLAGE ROAD EAST, FROM STREET GRAVESEND NECK ROAD TO STREET VILLAGE ROAD NORTH
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
A/T/P/O I OBSERVED THE ABOVE RESPONDENT/RESPONDENT'S SUB-CONTRACTORS HAD INSTALLED 40 FEET BY 7 FEET OF NEW SIDEWALK-WITHOUT A VALID DOT PERMIT TO DO SO. INSTALLATION OF SIDEWALK-NO PERMIT.NYC DEPT OF BUILDINGS PERMIT#320450436-01-
|
2017-10-24
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
s/w occupancy in complaince
|
2017-10-19
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Bricks stored.
|
2017-10-15
|
No data
|
VILLAGE ROAD EAST, FROM STREET GRAVESEND NECK ROAD TO STREET VILLAGE ROAD NORTH
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
A/T/P/O I OBSERVED THE ABOVE RESPONDENT/RESPONDENT'S SUB-CONTRACTORS HAD INSTALLED 40 FEET OF NEW CURB IN STREET-WITHOUT A VALID DOT PERMIT TO DO SO.(MORE THAN 25 FEET REQUIRES SEPARATE PERMIT).CURB INSTALLATION-NO PERMIT. NYC DEPT OF BUILDINGS
|
2017-10-01
|
No data
|
VILLAGE ROAD EAST, FROM STREET GRAVESEND NECK ROAD TO STREET VILLAGE ROAD NORTH
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
A/T/P/O I OBSERVED THE ABOVE RESPONDENT/RESPONDENT'S SUB-CONTRACTORS HAD INSTALLED 40 FEET BY 7 FEET OF NEW SIDEWALK-WITHOUT A VALID DOT PERMIT TO DO SO. INSTALLATION OF SIDEWALK-NO PERMIT.NYC DEPT OF BUILDINGS PERMIT#320450436-01-AL EXP 8/3/18 WAS
|
2017-09-15
|
No data
|
59 STREET, FROM STREET 18 AVENUE TO STREET 19 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Bricks stored in the p/l.
|