Inspection Type |
Referral
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2024-06-27
|
Emphasis |
N: FALL
|
Related Activity
Type |
Referral |
Activity Nr |
2152787 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260451 B05 II |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
6452.0 |
Initial Penalty |
6452.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(b)(5)(ii): The end of a platform greater than 10 feet in length extended over its support more than 18 inches and the platform was not designed and installed so that the cantilevered portion of the platform is able to support employees without tipping, or has guardrails which block employee access to the cantilevered end: a) Worksite - On or about April 17, 2024, employees were performing working on a Alum-A-Pole pump jack scaffold with a Werner platform approximately 29 feet above the ground. The platform was approximately 28 feet in length, the cantilevered end located below the access window was extended approximately 36 inches over the support. Employees were exposed to fall hazards. |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19260451 B10 |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
6452.0 |
Initial Penalty |
6452.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(b)(10): Scaffold components manufactured by different manufacturers were intermixed such that the components fit together with force and the scaffold's structural integrity was not maintained by the user: a) Worksite - On or about April 17, 2024, employees were exposed to fall hazards of approximately 29 feet due to the Alum-A-Pole pump jack scaffold was erected with intermixed parts that included a Werner extension ladder for a top rail and a Werner platform that were both not properly secured with the chain system in place for Alum-A-Pole. |
|
Citation ID |
01003 |
Citaton Type |
Serious |
Standard Cited |
19260451 E08 |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
6452.0 |
Initial Penalty |
6452.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(e)(8): Direct access to or from another surface was used when the scaffold was more than 14 inches (36 cm) horizontally and/or 24 inches (61 cm) vertically from the other surface: a) Worksite - On or about April 17, 2024, employees were exposed to fall hazards of approximately 29 feet due to direct access to the Werner platform on the Alum-A-Pole pump jack scaffold was through the window on the 3rd floor with the approximate horizontal distance between the platform of the scaffold and the window/wall of the building being 18 inches. |
|
Citation ID |
01004A |
Citaton Type |
Serious |
Standard Cited |
19260451 F06 |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
6452.0 |
Initial Penalty |
6452.0 |
Final Order |
2024-11-13 |
Nr Instances |
2 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(f)(6): Scaffolds were erected, used, dismantled, altered, or moved such that they, or any conductive material handled on them, could have come closer than the minimum distances established for specific voltages as set forth in the table in subparagraph (f)(6): a) Worksite - On or about April 16, 2024, employees erected an Alum-A-Pole pump jack scaffold within approximately 6.5 feet of an uninsulated power line with voltage of 13.2kV phase to phase and 7.62kV phase to ground exposing employees to electrocution hazards. The erection of this scaffold was within the minimum approach distance of 10 feet. b) Worksite - On or about April 17, 2024, employees worked from and used an Alum-A-Pole pump jack scaffold within approximately 5 feet from an uninsulated power line with voltage of 13.2kV phase to phase and 7.62kV phase to ground exposing employees to electrocution hazards. The use of this scaffold would be within the minimum approach distance of 10 feet. |
|
Citation ID |
01004B |
Citaton Type |
Serious |
Standard Cited |
19260451 F07 |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration: a) Worksite - On or about April 16, 2024, employees erected an Alum-A-Pole pump jack scaffold with the employees not being trained on scaffolding and there was no competent person at the worksite or within the company to supervise or direct the erection of the scaffold exposing employees to electrocution and fall hazards. |
|
Citation ID |
01005A |
Citaton Type |
Serious |
Standard Cited |
19260454 A |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
6452.0 |
Initial Penalty |
6452.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.454(a): The employer did not have each employee who performed work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards: a) Worksite - On or about April 17, 2024, employees working on an Alum-A-Pole pump jack scaffold were not trained by a person qualified in the subject matter to recognize hazards associated with the type of scaffold being used to include employees being exposed to fall hazards of approximately 29 feet and electrocution hazards due to working within the minimum approach distance when working near an uninsulated power line with voltage of 13.2kV phase to phase and 7.62kV phase to ground. |
|
Citation ID |
01005B |
Citaton Type |
Serious |
Standard Cited |
19260454 B |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.454(b): The employer did not have each employee involved in erecting, disassembling, moving, operating, repairing, maintaining, or inspecting a scaffold trained by a competent person to recognize any hazards associated with the work in question: a) Worksite - On or about April 16, 2024, employees erected an Alum-A-Pole pump jack scaffold with the employees not being trained on scaffolding by a competent person to recognize hazards associated with the type of scaffold being used to include employees being exposed to fall hazards of approximately 29 feet and electrocution hazards due to working within the minimum approach distance when working near an uninsulated power line with voltage of 13.2kV phase to phase and 7.62kV phase to ground. |
|
Citation ID |
01006 |
Citaton Type |
Serious |
Standard Cited |
19260451 G01 |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
6452.0 |
Initial Penalty |
6452.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(g)(1): Employees on scaffolds more than 10 feet (3.1 m) above a lower level were not protected from falling to that lower level by fall protection established in paragraphs (g)(1)(i)-(vii) of this section: a) Worksite - On or about April 17, 2024, employees worked on an Alum-A-Pole pump jack scaffold without fall protection, guardrails, and safety netting in place exposing the employees to fall hazards of approximately 29 feet. |
|
Citation ID |
01007 |
Citaton Type |
Serious |
Standard Cited |
19260451 G04 I |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
6452.0 |
Initial Penalty |
6452.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(g)(4)(i): Guardrail systems were not installed along all open sides and ends of platforms before being released for use by employees other than erection/dismantling crews: a) Worksite - On or about April 17, 2024, employees worked on an Alum-A-Pole pump jack scaffold without a guardrail system installed along all open sides and ends of platforms exposing the employees to fall hazards of approximately 29 feet. |
|
Citation ID |
01008 |
Citaton Type |
Serious |
Standard Cited |
19260452 J02 |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
6452.0 |
Initial Penalty |
6452.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
2 |
Related Event Code (REC) |
Referral |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.452(j)(2): Poles were not secured to the structure by rigid triangular bracing or equivalent at the bottom, top, and other points as necessary. a) Worksite - On or about April 17, 2024, employees worked on an Alum-A-Pole pump jack scaffold without bottom bracing installed exposing the employees to fall hazards of approximately 29 feet and electrocution hazards in the event the scaffold tipped over. |
|
Citation ID |
02001 |
Citaton Type |
Other |
Standard Cited |
19040029 A |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
922.0 |
Initial Penalty |
922.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
1 |
Related Event Code (REC) |
Referral |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1904.29(a): The employer did not use an OSHA 300, 301 and 300A Form or equivalent: a) Worksite - On or about April 17, 2024, an employee handled a piece of aluminum metal flashing/drip edge on an Alum-A-Pole pump jack scaffold that contacted an uninsulated power line with voltage of 13.2kV phase to phase and 7.62kV phase to ground exposing the employee to electrocution hazards. The employee was hospitalized and missed days away from work. The employer did not use an OSHA 300 Log or OSHA 301 or equivalent to record the injury. |
|
Citation ID |
02002 |
Citaton Type |
Other |
Standard Cited |
19040040 A |
Issuance Date |
2024-10-07 |
Abatement Due Date |
2024-10-11 |
Current Penalty |
922.0 |
Initial Penalty |
922.0 |
Final Order |
2024-11-13 |
Nr Instances |
1 |
Nr Exposed |
1 |
Related Event Code (REC) |
Referral |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1904.40(a): The employer did not provide an authorized government representative the records within the four business hours. a) Worksite - On or about April 17, 2024, an employee handled a piece of aluminum metal flashing/drip edge on an Alum-A-Pole pump jack scaffold that contacted an uninsulated power line with voltage of 13.2kV phase to phase and 7.62kV phase to ground exposing the employee to electrocution hazards. The employee was hospitalized and missed days away from work. Upon request phone call and email on 5/24/2024, the employer did not provide OSHA 300 Logs within four business hours. |
|
|